Author:
Publisher:
ISBN:
Category :
Languages : en
Pages : 170
Book Description
The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).
Environmental Assessment of the Gering-Stegall 115-kV Transmission Line Consolidation Project, Scotts Bluff County, Nebraska
Author:
Publisher:
ISBN:
Category :
Languages : en
Pages : 170
Book Description
The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).
Publisher:
ISBN:
Category :
Languages : en
Pages : 170
Book Description
The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).
Government Reports Announcements & Index
Author:
Publisher:
ISBN:
Category : Science
Languages : en
Pages : 1130
Book Description
Publisher:
ISBN:
Category : Science
Languages : en
Pages : 1130
Book Description
Medical Center for Federal Prisoners, Springfield, Missouri
Author: United States. Bureau of Prisons
Publisher:
ISBN:
Category : Prisons
Languages : en
Pages : 32
Book Description
Publisher:
ISBN:
Category : Prisons
Languages : en
Pages : 32
Book Description
Environmental Assessment
Author: United States. Western Area Power Administration. Loveland Area Office
Publisher:
ISBN:
Category : Electric lines
Languages : en
Pages : 242
Book Description
Publisher:
ISBN:
Category : Electric lines
Languages : en
Pages : 242
Book Description
Marys Lake 69/115-kV Transmission Line Upgrade and Substation Expansion Projects
Author:
Publisher:
ISBN:
Category :
Languages : en
Pages : 212
Book Description
Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.
Publisher:
ISBN:
Category :
Languages : en
Pages : 212
Book Description
Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.
Sidney-North Yuma 230-kV Transmission Line Project, Colorado and Nebraska
Author:
Publisher:
ISBN:
Category :
Languages : en
Pages : 212
Book Description
This report describes the need for a 230-kV overhead transmission line to supply power from Sidney, Nebraska to eastern Colorado. The alternative scenario compared to construction of the line is No Action. Rejected alternatives include underground lines and different routing paths, with a possible extension to the Sterling area. Both scenarios are evaluated for environmental effects, cost, and consequences for the eastern Colorado region. The proposed route is determined to be the environmentally preferred choice. 120 refs., 6 figs., 13 tabs. (MHB).
Publisher:
ISBN:
Category :
Languages : en
Pages : 212
Book Description
This report describes the need for a 230-kV overhead transmission line to supply power from Sidney, Nebraska to eastern Colorado. The alternative scenario compared to construction of the line is No Action. Rejected alternatives include underground lines and different routing paths, with a possible extension to the Sterling area. Both scenarios are evaluated for environmental effects, cost, and consequences for the eastern Colorado region. The proposed route is determined to be the environmentally preferred choice. 120 refs., 6 figs., 13 tabs. (MHB).
Grand Coulee-Bell 500-kV Transmission Line Project
Author:
Publisher:
ISBN:
Category :
Languages : en
Pages : 218
Book Description
Publisher:
ISBN:
Category :
Languages : en
Pages : 218
Book Description
Thermopolis-Alcova-Casper Transmission Line Project Wyoming
Author:
Publisher:
ISBN:
Category : Electric lines
Languages : en
Pages : 350
Book Description
Publisher:
ISBN:
Category : Electric lines
Languages : en
Pages : 350
Book Description
Thermopolis-Alcova-Casper Transmission Line Project Wyoming: Maps and Tables
Author:
Publisher:
ISBN:
Category : Electric lines
Languages : en
Pages : 0
Book Description
This EIS assesses the environmental effects of constructing 152.1 miles of 230-kV or 230/345-kV transmission line between Thermopolis and Alcova, and between Alcova and Casper. Approximately 136.1 miles of the new 230-kV or 230/345-kV line will either replace two existing but deteriorated 69-kV lines or parallel an existing 115-kV line. The remaining 16.0 miles of line will be constructed on a new corridor. In addition, approximately 50.0 miles of 69-kV line will be reconstructed at 69/115-kV between Arminto and Casper. Other minor elements of the project include construction of short 34.5-kV and 69/115-kV connecting lines, and a new substation near Alcova. The purpose of the project is to bring the regional transmission system into compliance with National Electric Reliability Council criteria and to reduce energy losses associated with overloading of the existing system. Alternatives assessed include no action, delay, reduction in the quality of electrical service, alternative transmission technologies, alternative design, and alternative routes. Significant impacts include soil disturbance and increased erosion, potential disturbance of sensitive habitats for sage grouse, bald eagles and raptors, and increased visual impacts created by the replacement of small, wood structures with larger transmission structures.
Publisher:
ISBN:
Category : Electric lines
Languages : en
Pages : 0
Book Description
This EIS assesses the environmental effects of constructing 152.1 miles of 230-kV or 230/345-kV transmission line between Thermopolis and Alcova, and between Alcova and Casper. Approximately 136.1 miles of the new 230-kV or 230/345-kV line will either replace two existing but deteriorated 69-kV lines or parallel an existing 115-kV line. The remaining 16.0 miles of line will be constructed on a new corridor. In addition, approximately 50.0 miles of 69-kV line will be reconstructed at 69/115-kV between Arminto and Casper. Other minor elements of the project include construction of short 34.5-kV and 69/115-kV connecting lines, and a new substation near Alcova. The purpose of the project is to bring the regional transmission system into compliance with National Electric Reliability Council criteria and to reduce energy losses associated with overloading of the existing system. Alternatives assessed include no action, delay, reduction in the quality of electrical service, alternative transmission technologies, alternative design, and alternative routes. Significant impacts include soil disturbance and increased erosion, potential disturbance of sensitive habitats for sage grouse, bald eagles and raptors, and increased visual impacts created by the replacement of small, wood structures with larger transmission structures.