Author: Ronald O'Rourke
Publisher: Createspace Independent Publishing Platform
ISBN: 9781545110621
Category :
Languages : en
Pages : 48
Book Description
The Coast Guard's acquisition program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The Coast Guard's proposed FY2017 budget requests a total of $467 million in acquisition funding for the NSC, OPC, and FRC programs. NSCs are the Coast Guard's largest and most capable general-purpose cutters. They have an estimated average procurement cost of about $695 million per ship. The first five are now in service. The sixth was delivered on December 16, 2016, and was scheduled to be commissioned into service on April 1, 2017. The seventh and eighth are under construction and scheduled for delivery in 2018 and 2019, respectively. A ninth NSC, which was not requested by the Coast Guard, was funded by Congress in FY2016; the Coast Guard awarded a production contract for the ship on December 30, 2016. The Coast Guard's proposed FY2017 budget requests $127 million in acquisition funding for the NSC program for postdelivery activities on NSCs 4 through 8, program close-out, follow-on test and evaluation, program support, and procurement of small unmanned aerial systems (UAS) for NSCs. OPCs are to be smaller, less expensive, and in some respects less capable than NSCs. They have an estimated average procurement cost of about $421 million per ship. The first OPC is to be procured in FY2018. Three shipyards-Bollinger Shipyards of Lockport, LA, Eastern Shipbuilding Group of Panama City, FL, and General Dynamics Bath Iron Works (GD/BIW) of Bath, ME-were competing for the contract to build the first 9 to 11 ships in the class. On September 15, 2016, the Coast Guard announced that it was awarding the contract to Eastern Shipbuilding. The Coast Guard's proposed FY2017 budget requests $100 million in acquisition funding for the OPC program for technical review of detail design (DD) deliverables and procurement of long lead time material (LLTM) for the first ship. FRCs are considerably smaller and less expensive than OPCs. They have an estimated average procurement cost of about $65 million per boat. A total of 38 have been funded through FY2016. The 19th was commissioned into service on November 19, 2016. The Coast Guard's proposed FY2017 budget requests $240 million in acquisition funding for the FRC program for the construction of four more FRCs. The NSC, OPC, and FRC programs pose several issues for Congress, including the following: whether to fund the acquisition of a 10th NSC in FY2017; whether to fund the acquisition of four FRCs in FY2017, as requested, or some other number, such as six, which was the number projected for FY2017 under the Coast Guard's FY2016 budget submission; whether to use annual or multiyear contracting for procuring FRCs; whether to use annual or multiyear contracting for procuring OPCs; planned procurement quantities for NSCs, OPCS, and FRCs; the cost, design, and acquisition strategy for the OPC; initial testing of the NSC; and rotational crewing of the NSC. Congress's decisions on these programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base.
Coast Guard Cutter Procurement
Author: Ronald O'Rourke
Publisher: Createspace Independent Publishing Platform
ISBN: 9781545110621
Category :
Languages : en
Pages : 48
Book Description
The Coast Guard's acquisition program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The Coast Guard's proposed FY2017 budget requests a total of $467 million in acquisition funding for the NSC, OPC, and FRC programs. NSCs are the Coast Guard's largest and most capable general-purpose cutters. They have an estimated average procurement cost of about $695 million per ship. The first five are now in service. The sixth was delivered on December 16, 2016, and was scheduled to be commissioned into service on April 1, 2017. The seventh and eighth are under construction and scheduled for delivery in 2018 and 2019, respectively. A ninth NSC, which was not requested by the Coast Guard, was funded by Congress in FY2016; the Coast Guard awarded a production contract for the ship on December 30, 2016. The Coast Guard's proposed FY2017 budget requests $127 million in acquisition funding for the NSC program for postdelivery activities on NSCs 4 through 8, program close-out, follow-on test and evaluation, program support, and procurement of small unmanned aerial systems (UAS) for NSCs. OPCs are to be smaller, less expensive, and in some respects less capable than NSCs. They have an estimated average procurement cost of about $421 million per ship. The first OPC is to be procured in FY2018. Three shipyards-Bollinger Shipyards of Lockport, LA, Eastern Shipbuilding Group of Panama City, FL, and General Dynamics Bath Iron Works (GD/BIW) of Bath, ME-were competing for the contract to build the first 9 to 11 ships in the class. On September 15, 2016, the Coast Guard announced that it was awarding the contract to Eastern Shipbuilding. The Coast Guard's proposed FY2017 budget requests $100 million in acquisition funding for the OPC program for technical review of detail design (DD) deliverables and procurement of long lead time material (LLTM) for the first ship. FRCs are considerably smaller and less expensive than OPCs. They have an estimated average procurement cost of about $65 million per boat. A total of 38 have been funded through FY2016. The 19th was commissioned into service on November 19, 2016. The Coast Guard's proposed FY2017 budget requests $240 million in acquisition funding for the FRC program for the construction of four more FRCs. The NSC, OPC, and FRC programs pose several issues for Congress, including the following: whether to fund the acquisition of a 10th NSC in FY2017; whether to fund the acquisition of four FRCs in FY2017, as requested, or some other number, such as six, which was the number projected for FY2017 under the Coast Guard's FY2016 budget submission; whether to use annual or multiyear contracting for procuring FRCs; whether to use annual or multiyear contracting for procuring OPCs; planned procurement quantities for NSCs, OPCS, and FRCs; the cost, design, and acquisition strategy for the OPC; initial testing of the NSC; and rotational crewing of the NSC. Congress's decisions on these programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base.
Publisher: Createspace Independent Publishing Platform
ISBN: 9781545110621
Category :
Languages : en
Pages : 48
Book Description
The Coast Guard's acquisition program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The Coast Guard's proposed FY2017 budget requests a total of $467 million in acquisition funding for the NSC, OPC, and FRC programs. NSCs are the Coast Guard's largest and most capable general-purpose cutters. They have an estimated average procurement cost of about $695 million per ship. The first five are now in service. The sixth was delivered on December 16, 2016, and was scheduled to be commissioned into service on April 1, 2017. The seventh and eighth are under construction and scheduled for delivery in 2018 and 2019, respectively. A ninth NSC, which was not requested by the Coast Guard, was funded by Congress in FY2016; the Coast Guard awarded a production contract for the ship on December 30, 2016. The Coast Guard's proposed FY2017 budget requests $127 million in acquisition funding for the NSC program for postdelivery activities on NSCs 4 through 8, program close-out, follow-on test and evaluation, program support, and procurement of small unmanned aerial systems (UAS) for NSCs. OPCs are to be smaller, less expensive, and in some respects less capable than NSCs. They have an estimated average procurement cost of about $421 million per ship. The first OPC is to be procured in FY2018. Three shipyards-Bollinger Shipyards of Lockport, LA, Eastern Shipbuilding Group of Panama City, FL, and General Dynamics Bath Iron Works (GD/BIW) of Bath, ME-were competing for the contract to build the first 9 to 11 ships in the class. On September 15, 2016, the Coast Guard announced that it was awarding the contract to Eastern Shipbuilding. The Coast Guard's proposed FY2017 budget requests $100 million in acquisition funding for the OPC program for technical review of detail design (DD) deliverables and procurement of long lead time material (LLTM) for the first ship. FRCs are considerably smaller and less expensive than OPCs. They have an estimated average procurement cost of about $65 million per boat. A total of 38 have been funded through FY2016. The 19th was commissioned into service on November 19, 2016. The Coast Guard's proposed FY2017 budget requests $240 million in acquisition funding for the FRC program for the construction of four more FRCs. The NSC, OPC, and FRC programs pose several issues for Congress, including the following: whether to fund the acquisition of a 10th NSC in FY2017; whether to fund the acquisition of four FRCs in FY2017, as requested, or some other number, such as six, which was the number projected for FY2017 under the Coast Guard's FY2016 budget submission; whether to use annual or multiyear contracting for procuring FRCs; whether to use annual or multiyear contracting for procuring OPCs; planned procurement quantities for NSCs, OPCS, and FRCs; the cost, design, and acquisition strategy for the OPC; initial testing of the NSC; and rotational crewing of the NSC. Congress's decisions on these programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base.
Coast Guard Cutter Procurement
Author: Ronald O'Rourke
Publisher: CreateSpace
ISBN: 9781500524760
Category : Political Science
Languages : en
Pages : 56
Book Description
The Coast Guard's program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The NSC, OPC, and FRC programs have a combined estimated acquisition cost of about $21.1 billion, and the Coast Guard's proposed FY2015 budget requests a total of $768 million in acquisition funding for the three programs.
Publisher: CreateSpace
ISBN: 9781500524760
Category : Political Science
Languages : en
Pages : 56
Book Description
The Coast Guard's program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The NSC, OPC, and FRC programs have a combined estimated acquisition cost of about $21.1 billion, and the Coast Guard's proposed FY2015 budget requests a total of $768 million in acquisition funding for the three programs.
Complex Contracting
Author: Trevor L. Brown
Publisher: Cambridge University Press
ISBN: 1107292662
Category : Business & Economics
Languages : en
Pages : 273
Book Description
Complex Contracting draws on core social science concepts to provide wide-ranging practical advice on how best to manage complex acquisitions. Using a strong analytical framework, the authors assess contract management practices, suggesting strategies for improvement and ways to avoid the pitfalls of managing contracts for large and sophisticated projects. An in-depth analysis of the US Coast Guard's Deepwater program is included to illustrate ways to respond to real-world contracting challenges. This high-profile and controversial case consisted of a projected 25-year, $24 billion contract through which the US Coast Guard would buy a system of new boats, aircraft, communications, and control architecture to replace its aging fleet. The authors explore the reasons why this program, launched with such promise, turned out so poorly, and apply the lessons learned to similarly complex contracting scenarios. This engaging and accessible book has broad applicability and will appeal to policymakers, practitioners, scholars and students.
Publisher: Cambridge University Press
ISBN: 1107292662
Category : Business & Economics
Languages : en
Pages : 273
Book Description
Complex Contracting draws on core social science concepts to provide wide-ranging practical advice on how best to manage complex acquisitions. Using a strong analytical framework, the authors assess contract management practices, suggesting strategies for improvement and ways to avoid the pitfalls of managing contracts for large and sophisticated projects. An in-depth analysis of the US Coast Guard's Deepwater program is included to illustrate ways to respond to real-world contracting challenges. This high-profile and controversial case consisted of a projected 25-year, $24 billion contract through which the US Coast Guard would buy a system of new boats, aircraft, communications, and control architecture to replace its aging fleet. The authors explore the reasons why this program, launched with such promise, turned out so poorly, and apply the lessons learned to similarly complex contracting scenarios. This engaging and accessible book has broad applicability and will appeal to policymakers, practitioners, scholars and students.
Coast Guard Readiness
Author: United States. Congress. House. Committee on Transportation and Infrastructure. Subcommittee on Coast Guard and Maritime Transportation
Publisher:
ISBN:
Category : National security
Languages : en
Pages : 76
Book Description
Publisher:
ISBN:
Category : National security
Languages : en
Pages : 76
Book Description
The U.S. Coast Guard
Author:
Publisher:
ISBN:
Category :
Languages : en
Pages : 268
Book Description
Publisher:
ISBN:
Category :
Languages : en
Pages : 268
Book Description
Maintaining Coast Guard Readiness
Author: United States. Congress. House. Committee on Transportation and Infrastructure. Subcommittee on Coast Guard and Maritime Transportation
Publisher:
ISBN:
Category : Government vessels
Languages : en
Pages : 132
Book Description
Publisher:
ISBN:
Category : Government vessels
Languages : en
Pages : 132
Book Description
Hearings
Author: United States. Congress. House. Committee on Merchant Marine and Fisheries
Publisher:
ISBN:
Category :
Languages : en
Pages : 1380
Book Description
Publisher:
ISBN:
Category :
Languages : en
Pages : 1380
Book Description
Department of Transportation and Related Agencies Appropriations for 1983
Author: United States. Congress. House. Committee on Appropriations. Subcommittee on Dept. of Transportation and Related Agencies Appropriations
Publisher:
ISBN:
Category : United States
Languages : en
Pages : 1016
Book Description
Publisher:
ISBN:
Category : United States
Languages : en
Pages : 1016
Book Description
Department of Transportation and related agencies appropriations for fiscal year 1983
Author: United States. Congress. Senate. Committee on Appropriations. Subcommittee on Transportation and Related Agencies
Publisher:
ISBN:
Category :
Languages : en
Pages : 1032
Book Description
Publisher:
ISBN:
Category :
Languages : en
Pages : 1032
Book Description
Reports and Documents
Author: United States. Congress
Publisher:
ISBN:
Category :
Languages : en
Pages : 1842
Book Description
Publisher:
ISBN:
Category :
Languages : en
Pages : 1842
Book Description